Construction of Flood Mitigation Structure22FC0109

Construction of Flood Mitigation Structure of Mabulao Creek along Barangay 1, San Isidro Cobangbang Sections, Daet, Camarines Norte

Construction of Flood Mitigation Structure of Mabulao Creek along Barangay 1, San Isidro Cobangbang Sections, Daet, Camarines Norte is a DPWH-tracked public work in DAET (CAPITAL) (CAMARINES NORTE), CAMARINES NORTE, Region V. Reported contract value: ₱19,799,782.74. Status: Reported complete (DPWH). Contractor on record: 128 DRAGON CONST AND SUPPLIES. Figures trace to sumbong.

DAET (CAPITAL) (CAMARINES NORTE), CAMARINES NORTE, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure of Mabulao Creek along Barangay 1, San Isidro Cobangbang Sections, Daet, Camarines Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002900

₱1,325,575,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002430

₱43,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

208 projects · ₱3.4B total · 2 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ROAD ALONG DAET RIVER, BARANGAY

Region V, Region V

2025₱96.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF BINATAGAN RIVER CONTROL STRUCTURE W/ ROAD (PHASE I)BARA

Region V, Region V

2024₱93.6M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)

Construction of Flood Control Structure along Basud River, Barangay San Jose, Basud, Camarines Norte

BASUD (CAMARINES NORTE), CAMARINES NORTE, Region V

2024₱86.8M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MANGCAMAGONG -MATOOG-TOOG SEAWALL, BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE AND BARANGAY MATOOG-TOOG, MERCEDES, CAMARINES NORTE

Camarines Norte DEO, Region V

2020₱74.9M
Reported complete (DPWH)
View all 208 projects →

4. Implementation

Contract Amount

₱19,799,782.74

Progress

Reported complete (DPWH)

Start Date

March 21, 2022

Target End

September 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.