Buildings and Facilities19MG0137

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM) WITH BLEACHERS, BARANGAY KLUBI, LAKE SEBU, SOUTH COTABATO

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM) WITH BLEACHERS, BARANGAY KLUBI, LAKE SEBU, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱1,479,056.95. Status: Reported complete (DPWH). Contractor on record: MRS BUILDERS AND SUPPLY. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-CAR-19-0019827

₱5,063,000.00 · FY2019

Released to Far North Luzon General Per Hospital and Training Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

180 projects · ₱1.0B total · 0 flags

4. Implementation

Contract Amount

₱1,479,056.95

Progress

Reported complete (DPWH)

Start Date

August 29, 2019

Target End

November 26, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.