Construction of Drainage Structure23A00077

Construction/Rehabilitation/lmprovement of 800 LM Canal Lining Barangay Barcelona, Solsona, Ilocos Norte

Construction/Rehabilitation/lmprovement of 800 LM Canal Lining Barangay Barcelona, Solsona, Ilocos Norte is a DPWH-tracked public work in SOLSONA (ILOCOS NORTE), ILOCOS NORTE, Region I. Reported contract value: ₱9,649,819.12. Status: Reported complete (DPWH). Contractor on record: RCD GEN CONTRACTOR & CONST SUPPLY. Figures trace to sumbong.

SOLSONA (ILOCOS NORTE), ILOCOS NORTE, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Subec, Pagudpud, Ilocos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Norte 2nd District Engineering Office · SARO 40 (₱23,603,513,542.02) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

21 projects · ₱700.6M total · 0 flags

4. Implementation

Contract Amount

₱9,649,819.12

Progress

Reported complete (DPWH)

Start Date

March 14, 2023

Target End

June 23, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.