Flood Control and Drainage23A00399

REPAIR/REHABILITATION OF FLOOD MITIGATION STRUCTURE ALONG TINA RIVER UPSTREAM/DOWNSTREAM OF TINA BRIDGE, TRAVERSING ILOCOS NORTE-APAYAO ROAD, SOLSONA, ILOCOS NORTE

REPAIR/REHABILITATION OF FLOOD MITIGATION STRUCTURE ALONG TINA RIVER UPSTREAM/DOWNSTREAM OF TINA BRIDGE, TRAVERSING ILOCOS NORTE-APAYAO ROAD, SOLSONA, ILOCOS NORTE is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱48,249,664.65. Status: Reported complete (DPWH). Contractor on record: RCD GEN CONTRACTOR & CONST SUPPLY. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

21 projects · ₱700.6M total · 0 flags

4. Implementation

Contract Amount

₱48,249,664.65

Progress

Reported complete (DPWH)

Start Date

June 14, 2023

Target End

January 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.