Buildings and Facilities18CG0059

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF BULAC MULTI-PURPOSE BUILDING, MINALIN, PAMPANGA

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF BULAC MULTI-PURPOSE BUILDING, MINALIN, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱1,409,118.05. Status: Reported complete (DPWH). Contractor on record: FROMARC BUILDERS. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱34,988,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Dawe River Sta. 0+000 - Sta. 3+150 at Minalin, Pampanga
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0014497

₱0.00 · FY2018

Released to Division of Pampanga (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

61 projects · ₱1.5B total · 0 flags

Other projects by this contractor

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONST OF REVETMENT ALONG ILANG-ILANG RIVER BRGY.ALAPAN SEC PHASE IV

Cavite 1st DEO, Region IV-A

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERSCONST OF REVETMENT ALONG JULIAN RIVER, BRGY MALAGASANG I-B, IMUS,

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 :PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROG CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS CONST OF REVETMENT ALONG JULIAN RIVER PHASE 1, BRGY. ANABU I-B IMUS

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERSCONST OF REVETMENT ALONG JULIAN RIVER, BRGY ANABU I-D, IMUS, CAV

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADSCARSADANG BAGO - MALAGASANG DIVERSION ROAD, ALAPAN - CARSADANG BAGO SECTION, CAVITE

Cavite 1st DEO, Region IV-A

2024₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSCARSADANG BAGO - MALAGASANG DIVERSION ROAD, BUCANDALA SECTION, SEGMENT 2, CAVITE

Cavite 1st DEO, Region IV-A

2024₱77.2M
Reported complete (DPWH)
View all 61 projects →

4. Implementation

Contract Amount

₱1,409,118.05

Progress

Reported complete (DPWH)

Start Date

April 23, 2018

Target End

June 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.