Flood Control and Drainage24OF0110

CONSTRUCTION OF DRAINAGE SYSTEMS AT FERCON AND CONNECTING DRAINAGES, BRGY. TANDANG SORA, QUEZON CITY

CONSTRUCTION OF DRAINAGE SYSTEMS AT FERCON AND CONNECTING DRAINAGES, BRGY. TANDANG SORA, QUEZON CITY is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱9,698,413.20. Status: Past target date (DPWH On-Going). Contractor on record: DJL ROBLES BUILDERS. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures and Drainage Systems at Brgy. Tandang Sora, Quezon City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quezon City 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,698,413.20

Progress

Past target date (DPWH On-Going)

Start Date

April 1, 2024

Target End

October 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.