Buildings and Facilities18OH0101

CONSTRUCTION OF MULTI-PURPOSE BUILDING,BRGY.795,SAN ANDRES BUKID,MANILA

CONSTRUCTION OF MULTI-PURPOSE BUILDING,BRGY.795,SAN ANDRES BUKID,MANILA is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱1,882,388.97. Status: Reported complete (DPWH). Contractor on record: ST MATTHEW GEN CONTRACTOR. Figures trace to dpwh.

South Manila DEO, National Capital Region
Region: National Capital Region

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱6,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-E-18-0012182 · ₱40,000 · release to the district office, not itemized per project

    Possible match · score 0.76

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18OH0101 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-08-10 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING,BRGY.795,SAN ANDRES BUKID,MANILA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Drainage along A. Francisco St., San Andres Bukid, Manila City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0012182

₱40,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,882,388.97

Progress

Reported complete (DPWH)

Start Date

May 15, 2018

Target End

August 12, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.