Buildings and Facilities16ED0069No coordinates published by DPWH

CONSTRUCTION OF 2 BUILDINGS - 2 STOREY / 8 CLASSROOMS @ COMMUNITY VOCATIONAL HIGH SCHOOL, CALAPAN CITY, ORIENTAL MINDORO

CONSTRUCTION OF 2 BUILDINGS - 2 STOREY / 8 CLASSROOMS @ COMMUNITY VOCATIONAL HIGH SCHOOL, CALAPAN CITY, ORIENTAL MINDORO is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱21,964,342.05. Status: Reported complete (DPWH). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B

DPWH did not publish coordinates for this project. Location estimated from the project title (town level only); satellite images may not show the exact site.

Region: Region IV-B

No before/after satellite images: DPWH did not publish coordinates, and the location estimated from the project title is only town level, which is not confident enough to image.

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2016 · ₱30,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROVIII-16-0001091 · ₱98,182 · release to the district office, not itemized per project

    Possible match · score 0.71

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱21,964,342 · MONOLITHIC CONSTRUCTION AND CONCRETE PRODUCTS, .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · School building, cost per classroom (new school building)

₱2,745,543 per classroom= 2.0x the Region IV-B median (n=302)

Contract cost ₱21,964,342 ÷ 8 classroom read from the DPWH title (“8 CLASSROOMS”; classroom count in title). National percentile: 88. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 2 BUILDINGS - 2 STOREY / 8 CLASSROOMS @ COMMUNITY VOCATIONAL HIGH SCHOOL, CALAPAN CITY, ORIENTAL MINDORO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Mag - Asawang Tubig and Allied Rivers Flood Mitigation/Control Projects, Rehabilitation/Construction of Gabion Revetment at Naujan (Mag - Asawang Tubig), Mindoro Oriental
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0001091

₱98,182.00 · FY2016

Released to Eastern Samar National Comprehensive High SchTer (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Const. of 2 Buildings - 2 Storey / 8 CL CVHS

₱21,964,342.05 · MONOLITHIC CONSTRUCTION AND CONCRETE PRODUCTS, .

Award / contract ref: 16ED0069

Contractor

B

299 projects · ₱22.3B total · 0 flags

4. Implementation

Contract Amount

₱21,964,342.05

Progress

Reported complete (DPWH)

Start Date

September 20, 2016

Target End

February 16, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.