Roads25CM0010

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, JOSE ABAD SANTOS AVE (JASA), K0118+753 - K0118+854, K0119+153 - K0119+160, K0119+186 - K0119+273, K0119+847 - K0119+946, K0120+789 - K0120+802, OLONGAPO CITY

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, JOSE ABAD SANTOS AVE (JASA), K0118+753 - K0118+854, K0119+153 - K0119+160, K0119+186 - K0119+273, K0119+847 - K0119+946, K0120+789 - K0120+802, OLONGAPO CITY is a DPWH-tracked public work in Zambales 2nd DEO, Region III. Reported contract value: ₱65,870,619.75. Status: Past target date (DPWH On-Going). Contractor on record: JAMJLE PROPERTIES SUBIC AND DEVELOPMENT CORPORAT. Figures trace to dpwh.

Zambales 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Riverbank Structure along Santo Tomas River (Omaya-Balingcaguing-Paite Section), San Narciso, Zambales (Phase 1)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Zambales 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱65,870,619.75

Progress

Past target date (DPWH On-Going)

Start Date

June 3, 2025

Target End

February 27, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.