BRIDGE PROGRAM-1.)RETROFITTING/ STRENGHTENING OF PERMANENT BRIDGES-AGUANG BRIDGE (BO3015LZ) ALONG BALER-CASIGURAN ROAD (BALER-DINADIAWAN, AND 2.) REHAB./MAJOR REPAIR OF PERMANENT BRIDGES-MALUPA BRIDGE (BO3007LZ) ALONG CASTANEDA-MA. AURORA-SAN LUIS ROAD
BRIDGE PROGRAM-1.)RETROFITTING/STRENGHTENING OF PERMANENT BRIDGES-AGUANG BRIDGE (BO3015LZ) ALONG BALER-CASIGURAN ROAD (BALER-DINADIAWAN, AND 2.) REHAB./MAJOR REPAIR OF PERMANENT BRIDGES-MALUPA BRIDGE (BO3007LZ) ALONG CASTANEDA-MA. AURORA-SAN LUIS ROAD is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱40,620,756.56. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ALPHATEC CHEMICAL CORP. Figures trace to dpwh.
Total Contract Cost