Bridges24J00113

WIDENING OF PERMANENT BRIDGES - COLOY BRIDGE (B00483MN) ALONG LANAO - PAGADIAN - ZAMBOANGA CITY RD

WIDENING OF PERMANENT BRIDGES - COLOY BRIDGE (B00483MN) ALONG LANAO - PAGADIAN - ZAMBOANGA CITY RD is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱14,315,680.23. Status: Past target date (DPWH On-Going). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images pending: this project is in the imagery queue (completed projects first, then ongoing). Before/after images will appear here when it is processed.

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24J00113 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    55% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: WIDENING OF PERMANENT BRIDGES - COLOY BRIDGE (B00483MN) ALONG LANAO - PAGADIAN - ZAMBOANGA CITY RD

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,028 projects · ₱22.5B total · 0 flags

4. Implementation

Contract Amount

₱14,315,680.23

Progress

Past target date (DPWH On-Going)

Start Date

March 25, 2024

Target End

July 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.