Construction of Flood Mitigation Structure23HC0039

Construction of Seawall, Cuya, Ubay, Bohol

Construction of Seawall, Cuya, Ubay, Bohol is a DPWH-tracked public work in UBAY (BOHOL), BOHOL, Region VII. Reported contract value: ₱48,999,999.44. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST & ENT INC FORMERLY R. Figures trace to sumbong.

UBAY (BOHOL), BOHOL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Macaas Flood Control, Macaas, Tubigon, Bohol
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bohol 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

36 projects · ₱2.1B total · 0 flags

4. Implementation

Contract Amount

₱48,999,999.44

Progress

Reported complete (DPWH)

Start Date

March 29, 2023

Target End

February 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.