Flood Control and Drainage23CL0043

REHABILITATION OF FLOOD CONTROL STRUCTURE AT BUCAO RIVER, UPSTREAM, PHASE VII, BOTOLAN, ZAMBALES

REHABILITATION OF FLOOD CONTROL STRUCTURE AT BUCAO RIVER, UPSTREAM, PHASE VII, BOTOLAN, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱96,497,043.20. Status: Past target date (DPWH On-Going). Contractor on record: GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Bucao River North Approach Downstream Phase 2, Botolan, Zambales
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zambales 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

39 projects · ₱3.4B total · 3 flags

Other projects by this contractor

No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. ALAS-ASI-IPAG, MARIVELES, BATAAN (PACKAGE 1),

Region III, Region III

2023₱289.5M
Past target date (DPWH On-Going)

Construction of Flood Control Structure (River Training Works) along Mompong River (Downstream), Sablayan, Occidental Mindoro

SABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS DAANG MAHARLIKA (LZ) - K0078 + 722 - K0079 + 366, K0090 + 042 - K0090 + 663, K0090 + 956 - K0091 + 353

Region IV-A, Region IV-A

2024₱244.0M
Past target date (DPWH On-Going)

Construction of Shore Protection and Coastal Road Development along Barangay Poblacion 2, Sta. Cruz, Occidental Mindoro

SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2023₱241.2M
Reported complete (DPWH)

Construction of Road Dike/Esplanade along Pangalaan River (Right Side), Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱241.2M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 2, BRGY. SAN LUIS, NAUJAN, OR. MINDOR

Region IV-B, Region IV-B

2024₱234.3M
Past target date (DPWH On-Going)
View all 39 projects →

4. Implementation

Contract Amount

₱96,497,043.20

Progress

Past target date (DPWH On-Going)

Start Date

March 28, 2023

Target End

June 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.