Roads18LF0021

ROAD WIDENING (2 INTO 4 LANES) ALONG COMPOSTELA-CATEEL ROAD (DAVAO OR. SIDE) INCL. RROW, K1566+865 TO 1567+160, K1567+292 TO 1568+464, K1568+971 TO 1569+683

ROAD WIDENING (2 INTO 4 LANES) ALONG COMPOSTELA-CATEEL ROAD (DAVAO OR. SIDE) INCL. RROW, K1566+865 TO 1567+160, K1567+292 TO 1568+464, K1568+971 TO 1569+683 is a DPWH-tracked public work in Davao Oriental 1st DEO, Region XI. Reported contract value: ₱75,413,506.22. Status: Reported complete (DPWH). Contractor on record: MAVERICK BUILDERS INC FORMERLY MAVERICK. Figures trace to dpwh.

Davao Oriental 1st DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱31,200,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment along Cateel River Protecting Compostela-Cateel Road (Davao Or. Side) Udiongan Section, Cateel, Davao Oriental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-LGRCB-18-0025292

₱50,900,000.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱75,413,506.22

Progress

Reported complete (DPWH)

Start Date

April 19, 2018

Target End

July 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.