Roads23II0062

CONCRETING OF BRGY. CATIGBIAN TO BRGY. PALMERA FMR, BRGY. CATIGBIAN AND BRGY. PALMERA, LAOANG, NORTHERN SAMAR

CONCRETING OF BRGY. CATIGBIAN TO BRGY. PALMERA FMR, BRGY. CATIGBIAN AND BRGY. PALMERA, LAOANG, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 2nd DEO, Region VIII. Reported contract value: ₱9,934,479.20. Status: Reported complete (DPWH). Contractor on record: JUPA CONST. Figures trace to dpwh.

Northern Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Concreting of Flood Control Carriageway in Barangay Cagamutan, Gamay, Northern Samar
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Northern Samar 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

117 projects · ₱4.4B total · 2 flags

4. Implementation

Contract Amount

₱9,934,479.20

Progress

Reported complete (DPWH)

Start Date

August 4, 2023

Target End

December 1, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.