Roads23O00002

CONSTRUCTION OF ROAD, PASIG RIVER ESPLANADE FROM AYALA BRIDGE TO JONES BRIDGE ALONG PASIG RIVER, MANILA (PHASE II) (RE-ADVERTISEMENT)

CONSTRUCTION OF ROAD, PASIG RIVER ESPLANADE FROM AYALA BRIDGE TO JONES BRIDGE ALONG PASIG RIVER, MANILA (PHASE II) (RE-ADVERTISEMENT) is a DPWH-tracked public work in National Capital Region, National Capital Region. Reported contract value: ₱76,023,130.26. Status: Past target date (DPWH On-Going). Contractor on record: J H PAJARA CONST CORP. Figures trace to dpwh.

National Capital Region, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

89 projects · ₱15.7B total · 0 flags

Other projects by this contractor

View all 89 projects →

4. Implementation

Contract Amount

₱76,023,130.26

Progress

Past target date (DPWH On-Going)

Start Date

July 21, 2023

Target End

November 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.