Bridges19C00023

BRIDGE CONSTRUCTION AND REPLACEMENT PROGRAM II (BCRP II) - PAMPANGA DELTA BRIDGE AND APPROACHES, MASANTOL, PAMPANGA

BRIDGE CONSTRUCTION AND REPLACEMENT PROGRAM II (BCRP II) - PAMPANGA DELTA BRIDGE AND APPROACHES, MASANTOL, PAMPANGA is a DPWH-tracked public work in Bridges Management Cluster, Central Office. Reported contract value: ₱566,628,265.70. Status: Past target date (DPWH On-Going). Contractor on record: J H PAJARA CONST CORP. Figures trace to dpwh.

Bridges Management Cluster, Central Office
Region: Central Office

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

89 projects · ₱15.7B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FLYOVER ALONG DAVAO CITY DIVERSION ROAD (JCT. MAGTUOD/MAA SECTION), DAVAO CITY

Region XI, Region XI

2022₱1.4B
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF DAVAO CITY COASTAL ROAD (TALOMO SECTION) - DAVAO - BUKIDNON ROAD (CATALUNAN PEQUEÑO - MINTAL SECTION - CALINAN SECTION) BYPASS ROAD (VIADUCT), BARANGAY TALOMO PROPER AND BARANGAY CATALUNAN PEQUEÑO, DAVAO CITY

Region XI, Region XI

2022₱570.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: WIDENING OF SAN LORENZO RUIZ BRIDGE (B01235LZ) (PARALLEL BRIDGE) ALONG DAANG MAHARLIKA (LZ)

Region II, Region II

2020₱384.8M
Past target date (DPWH On-Going)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES: PINARIPAD BRIDGE (B01214LZ) ALONG CDMA (DALEMDEM-PINARIPAD-PALACIAN) BY-PASS ROAD, AGLIPAY, QUIRINO

Region II, Region II

2019₱350.0M
Reported complete (DPWH)
No sat.

SAN MIGUEL BRIDGE (BO4187LZ) ALONG SAN SIMON-BALIWAG ROAD IN SAN SIMON, PAMPANGA, UNDER BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) 1, PROVINCE OF PAMPANGA

Bridges Management Cluster, Central Office

2021₱316.5M
Past target date (DPWH On-Going)
No sat.

CLUSTER 27 ROAD WIDENING IN MISAMIS ORIENTAL, 1) BCIR - K1477+397-K1478+068, K1478+094-K1479+691, K1479+722-K1480+582, K1480+602-K1483+640. 2) BCIR - K1484+286-K1487+299,K1487+351-K1491+000,K1491+000-K1491+248.

Region X, Region X

2018₱306.4M
Reported complete (DPWH)
View all 89 projects →

4. Implementation

Contract Amount

₱566,628,265.70

Progress

Past target date (DPWH On-Going)

Start Date

October 16, 2019

Target End

March 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.