Buildings and Facilities17IF0143No coordinates published by DPWH

CY 2017 BEFF (CONSTRUCTION OF CLASSROOMS) CONSTRUCTION OF TWO-STOREY SIX CLASSROOMS SCHOOL BUILDING, MATICA-A NATIONAL HIGH SCHOOL, ORMOC CITY

CY 2017 BEFF (CONSTRUCTION OF CLASSROOMS) CONSTRUCTION OF TWO-STOREY SIX CLASSROOMS SCHOOL BUILDING, MATICA-A NATIONAL HIGH SCHOOL, ORMOC CITY is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱11,429,393.75. Status: Reported complete (DPWH). Contractor on record: JA ACHACOSO ENT. Figures trace to dpwh.

Leyte 4th DEO, Region VIII

DPWH did not publish coordinates for this project. Location estimated from the project title (barangay level); satellite images may not show the exact site.

Region: Region VIII

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱20,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-B-17-0021054 · ₱487,933 · release to the district office, not itemized per project

    Possible match · score 0.66

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17IF0143 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CY 2017 BEFF (CONSTRUCTION OF CLASSROOMS) CONSTRUCTION OF TWO-STOREY SIX CLASSROOMS SCHOOL BUILDING, MATICA-A NATIONAL HIGH SCHOOL, ORMOC CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pagsanga-an Flood Control, Brgy. Lilo-an, Ormoc City, Leyte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-17-0021054

₱487,933.00 · FY2017

Released to 'Amang' Rodriguez Re Medical Center fo (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

132 projects · ₱3.0B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION OF THE REGIONAL CULTURAL HUB, PHASE I, TAGBILARAN CITY, BOHOL PROVINCE

Region VII, Region VII

2021₱135.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE, PACKAGE 2, BARANGAY STO NIÑO - BARANGAY MINDANAO, MALABU

Cebu 7th DEO, Region VII

2025₱97.5M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING PALOMPON - ISABEL - MERIDA - ORMOC ROAD K1098+000 - K1101+416

Leyte 4th DEO, Region VIII

2018₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) - AS PER R.A. 11239, CONSTRUCTION AND INSTALLATION OF SOLAR STREETLIGHTS, SAFETY SIGNS AND DEVICES - K0065+000 - K0072+000, ARGAO, CEBU

Cebu 2nd DEO, Region VII

2021₱96.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF SHORELINE PROTECTION STRUCTURES - JCT. HIMAY-ANGAN - SILAGO - ABUYOG BDRY. RD. (S00228LT) - ALONG ST. BERNARD SECTION, SOUTHERN LEYTE

Region VIII, Region VIII

2023₱89.8M
Past target date (DPWH On-Going)

CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE - JCT. HIMAY-ANGAN - SILAGO - ABUYOG BDRY. RD. - (S00228LT) ALONG SAN JUAN SECTION, SOUTHERN LEYTE

Region VIII, Region VIII

2023₱85.6M
Reported complete (100% progress, DPWH status On-Going)
View all 132 projects →

4. Implementation

Contract Amount

₱11,429,393.75

Progress

Reported complete (DPWH)

Start Date

December 18, 2017

Target End

May 6, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.