Buildings and Facilities20PD0088

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-REHABILITATION OF BARANGAY MULTI-PURPOSE HALL, BAGUIO CITY

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-REHABILITATION OF BARANGAY MULTI-PURPOSE HALL, BAGUIO CITY is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱1,908,102.80. Status: Reported complete (DPWH). Contractor on record: RNQ CONST AND ENGINEERING SERVICES. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱22,886,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Facilities along Balili River (Tributaries), Baguio City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Baguio City DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,908,102.80

Progress

Reported complete (DPWH)

Start Date

October 25, 2020

Target End

March 23, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.