Roads24N00158

CONSTRUCTION OF GUINABSAN-LOMBUYAN ROAD, BUENAVISTA, AGUSAN DEL NORTE (PHASE IV)

CONSTRUCTION OF GUINABSAN-LOMBUYAN ROAD, BUENAVISTA, AGUSAN DEL NORTE (PHASE IV) is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱97,956,889.88. Status: Past target date (DPWH On-Going). Contractor on record: ME 3 CONST. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱97,956,889.88

Progress

Past target date (DPWH On-Going)

Start Date

July 12, 2024

Target End

May 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.