Buildings and Facilities20FC0026

CONSTRUCTION OF A MULTI-PURPOSE BUILDING MANGCAYO ELEMENTARY SCHOOL, BRGY. MANGCAYO, VINZONS CAMS. N

CONSTRUCTION OF A MULTI-PURPOSE BUILDING MANGCAYO ELEMENTARY SCHOOL, BRGY. MANGCAYO, VINZONS CAMS. N is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱3,604,631.96. Status: Reported complete (DPWH). Contractor on record: GVENTURES INC. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control River at Brgy. Dallas, Labo, Camarines Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Camarines Norte DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

17 projects · ₱71.1M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING), SAN LORENZO RUIZ, CAMARINES NORTE

Camarines Norte DEO, Region V

2022₱9.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTIPURPOSE (SENIOR CITIZENS BUILDING), WITH COVERED COURT BARANGAY GUINACUTAN VINZON, CAMA

Region V, Region V

2024₱9.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 3, MERCEDES, CAMARINES NORTE

Camarines Norte DEO, Region V

2022₱5.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM(BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAMBUNGALON ELEMENTARY SCHOOL, BARANGAY MAMBUNGALON, MERCEDES, CAMAR

Region V, Region V

2023₱4.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY MANMUNTAY, BASUD, CAMARINES NORTE, BASUD, CAMAR

Region V, Region V

2025₱4.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT), OLIVA ELEMENTARY SCHOOL, BARANGAY OLIVA, BAS

Region V, Region V

2023₱4.0M
Reported complete (DPWH)
View all 17 projects →

4. Implementation

Contract Amount

₱3,604,631.96

Progress

Reported complete (DPWH)

Start Date

February 11, 2020

Target End

August 22, 2020

5. Audit