Buildings and Facilities18IC0091

CONST. OF ONE-STOREY, TWO-CLASSROOM SCHOOL BUILDING, (9.5MX18.0M) WITH PARAPET, STA. CRUZ ELEMENTARY SCHOOL, SAN MIGUEL, LEYTE

CONST. OF ONE-STOREY, TWO-CLASSROOM SCHOOL BUILDING, (9.5MX18.0M) WITH PARAPET, STA. CRUZ ELEMENTARY SCHOOL, SAN MIGUEL, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱4,017,891.71. Status: Reported complete (DPWH). Contractor on record: XED'S CONST. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱44,069,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control Wall along Bangon River, Sta. 4+032- Sta.4+571, Palo Section, Palo, Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-18-0003815

₱482,159.00 · FY2018

Released to Division of Southern (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

11 projects · ₱45.3M total · 0 flags

4. Implementation

Contract Amount

₱4,017,891.71

Progress

Reported complete (DPWH)

Start Date

December 4, 2018

Target End

March 28, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.