Roads17BD0099

CONCRETING OF PADUL FMR, PADUL, SOLANA, CAGAYAN

CONCRETING OF PADUL FMR, PADUL, SOLANA, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱1,889,941.94. Status: Reported complete (DPWH). Contractor on record: TECKCON CONST 33214. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 33214

24 projects · ₱221.8M total · 0 flags

Other projects by this contractor

No sat.

NATIONAL BUILDING PROGRAM - MULTIPURPOSE/FACILITIES - STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS/QUARANTINE FACILITIES - CAR, CONSTRUCTION OF EVACUATION CENTER AT POBLACION, KABUGAO, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2021₱35.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SOLANA DIVERSION ROAD PHASE II, SOLANA, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱34.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF FARM TO MILL ROAD, BRGY. SAMPAGUITA-BANTAY, SOLANA, CAGAYAN, STA. 0+000-STA. 0+35.38, STA. 0+40.70-STA. 0+119, STA. 0+305.09-STA. 0+854.21, STA. 1+354.03-STA. 1+805.33, STA. 2+497.04-STA. 3+892

Cagayan 3rd DEO, Region II

2016₱27.1M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF BUNOT FLOOD CONTROL, PARACELIS, MOUNTAIN PROVINCE

Mountain Province 2nd DEO, Cordillera Administrative Region

2020₱24.2M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION OF FLOOD MITIGATION STRUCTURES-CONSTRUCTION OF KATAO FLOOD CONTROL, PARACELIS, MOUNTAIN PROVINCE

Mountain Province 2nd DEO, Cordillera Administrative Region

2020₱24.1M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONSTRUCTION OF VARIOUS LOCAL ROADS AND DRAINAGES IN MUNICIPALITY OF SOLANA, CAGAYAN

Cagayan 3rd DEO, Region II

2021₱12.4M
Reported complete (DPWH)
View all 24 projects →

4. Implementation

Contract Amount

₱1,889,941.94

Progress

Reported complete (DPWH)

Start Date

June 8, 2017

Target End

August 6, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.