Buildings and Facilities17GP0190No coordinates published by DPWH

CONSTRUCTION OF TAMULALOD ES (DUMARAO)(1STY 3CL)

CONSTRUCTION OF TAMULALOD ES (DUMARAO)(1STY 3CL) is a DPWH-tracked public work in Capiz 2nd DEO, Region VI. Reported contract value: ₱3,690,261.64. Status: Reported complete (DPWH). Contractor on record: BPJ CONST AND SUPPLY. Figures trace to dpwh.

Capiz 2nd DEO, Region VI

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region VI

No before/after satellite images: DPWH has not published map coordinates for this project, so there is no location to image.

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱35,000 (shared by many projects, not this project's own line)

    Possible match · score 0.79

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-17-0010836 · ₱277,253 · release to the district office, not itemized per project

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17GP0190 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF TAMULALOD ES (DUMARAO)(1STY 3CL)

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Cadio Flood Control along Panay River, Capiz
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0010836

₱277,253.00 · FY2017

Released to Salvacion National High School - Bato (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱3,690,261.64

Progress

Reported complete (DPWH)

Start Date

January 11, 2018

Target End

May 5, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VI (Western Visayas)Capiz
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Dry conditions likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.