CONSTRUCTION OF FOOTBRIDGE ALONG KILOMETER 13+941 MAC ARTHUR HIGHWAY, BRGY. MALINTA, VALENZUELA CITY

CONSTRUCTION OF FOOTBRIDGE ALONG KILOMETER 13+941 MAC ARTHUR HIGHWAY, BRGY. MALINTA, VALENZUELA CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱2,218,701.87. Status: Reported complete (DPWH). Contractor on record: CARRY-ON CONST. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: National Capital Region

No before/after satellite images: DPWH has not published map coordinates for this project, so there is no location to image.

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱25,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-17-0019987 · ₱15,125 · release to the district office, not itemized per project

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17OD0094 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FOOTBRIDGE ALONG KILOMETER 13+941 MAC ARTHUR HIGHWAY, BRGY. MALINTA, VALENZUELA CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall/Riprapping along the Banks of various Creeks in Brgy. 175), Caloocan City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0019987

₱15,125.00 · FY2017

Released to Barcelona National Comprehensive High School Allot di pe (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,218,701.87

Progress

Reported complete (DPWH)

Start Date

May 23, 2017

Target End

September 19, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.