Buildings and Facilities18FH0261

CONSTRUCTIO(COMPLETION) OF THREE STOREY SIX CLASSROOM-TWO UNITS (7X18) SCIENCE LABORATORY,TOE UNITS (7X18) ICT LABORATORY & TWO UNITS (7X18) CLASSROOM REGULAR WORKSHOP SCHOOL BUILDING, MABATO NATIONAL HIGH SCHOOL, (SMRDHS ANNEX) SAN MIGUEL

CONSTRUCTIO(COMPLETION) OF THREE STOREY SIX CLASSROOM-TWO UNITS (7X18) SCIENCE LABORATORY,TOE UNITS (7X18) ICT LABORATORY & TWO UNITS (7X18) CLASSROOM REGULAR WORKSHOP SCHOOL BUILDING, MABATO NATIONAL HIGH SCHOOL, (SMRDHS ANNEX) SAN MIGUEL is a DPWH-tracked public work in Catanduanes DEO, Region V. Reported contract value: ₱3,440,772.46. Status: Reported complete (DPWH). Contractor on record: CHRISMAN CONST. Figures trace to dpwh.

Catanduanes DEO, Region V
Region: Region V

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-18-0017466 · · release to the district office, not itemized per project

    Possible match · score 0.81

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18FH0261 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-04-22 → 2021-05-23

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTIO(COMPLETION) OF THREE STOREY SIX CLASSROOM-TWO UNITS (7X18) SCIENCE LABORATORY,TOE UNITS (7X18) ICT LABORATORY & TWO UNITS (7X18) CLASSROOM REGULAR WORKSHOP SCHOOL BUILDING, MABATO NATIONAL HIGH SCHOOL, (SMRDHS ANNEX) SAN MIGUEL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Drainage Structure at Poblacion, San Andres, Catanduanes
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0017466

₱0.00 · FY2018

Released to Division of Catanduanes (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

61 projects · ₱765.7M total · 0 flags

Other projects by this contractor

No sat.

CONST. OF FOUR (4) STOREY SIXTEEN (16) CLASSROOM-TWO(2) UNITS (7 X 18) SCIENCE LABORATORY, TWO(2) UNITS (7 X 18) ICT LABORATORY & EIGHT (8) CLASSROOM (7 X 9) SENIOR HIGH SCHOOL BUILDING, SAN ANDRES VOCATIONAL SCHOOL, SAN ANDRES (CALOLBON), CATANDUANES

Catanduanes DEO, Region V

2018₱50.9M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF THREE (3) STOREY EIGHTEEN (18) CLASSROOM (7MX9M) SCHOOL BUILDING, SAN ANDRES VOCATIONAL SCHOOL, SAN ANDRES, CATANDUANES

Catanduanes DEO, Region V

2016₱42.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FOUR(4) STOREY TEN (10) CLASSROOM-TWO(2) UNITS (7 X 18) SCIENCE LABORATORY, TWO(2) UNITS (7 X 18) ICT LABORATORY, TWO(2) UNITS (7 X 18) REGULAR WORKSHOP & FOUR(4) CLASSROOM (7 X 9) CLASSROOM SENIOR HS BUILDING, CABCAB NHS, SAN ANDRES, CATA

Catanduanes DEO, Region V

2018₱40.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF THREE (3) STOREY FIFTEEN (15) CLASSROOM (7MX9M) SCHOOL BULDING, PANDAN SCHOOL OF ARTS AND TRADE, PANDAN, CATANDUANES

Catanduanes DEO, Region V

2016₱38.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FOUR(4) STOREY SIXTEEN (16) CLASSROOM-SIX(6) UNITS (7 X 18) REGULAR WORKSHOP & FOUR(4) CLASSROOM (7 X 9) SENIOR HIGH SCHOOL BUILDING, BARAS RURAL DEVELOPMENT HIGH SCHOOL, BARAS, CATANDUANES

Catanduanes DEO, Region V

2018₱36.4M
Reported complete (DPWH)
No sat.

IMPROVEMENT/REHABILITATION OF DPWH BUILDING-CATANDUANES DISTRICT ENGINEERING OFFICE, SAN ISIDRO VILLAGE, VIRAC, CATANDUANES

Catanduanes DEO, Region V

2019₱34.3M
Reported complete (DPWH)
View all 61 projects →

4. Implementation

Contract Amount

₱3,440,772.46

Progress

Reported complete (DPWH)

Start Date

December 14, 2018

Target End

February 11, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)CatanduanesSan MiguelMabato
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →