Roads24MF0024

CONSTRUCTION OF ROAD FROM BARANGAY LUMUYON TO BARANGAY POLOMOLOK, MUNICIPALITY OF COLUMBIO, PROVINCE OF SULTAN KUDARAT

CONSTRUCTION OF ROAD FROM BARANGAY LUMUYON TO BARANGAY POLOMOLOK, MUNICIPALITY OF COLUMBIO, PROVINCE OF SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 1st DEO, Region XII. Reported contract value: ₱9,511,909.19. Status: Reported complete (DPWH). Contractor on record: FPJ CONST AND SUPPLY. Figures trace to dpwh.

Sultan Kudarat 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Poblacion, Kalamansig, Sultan Kudarat
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Sultan Kudarat 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,511,909.19

Progress

Reported complete (DPWH)

Start Date

February 15, 2024

Target End

July 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.