Construction of Flood Mitigation Structure24CD0131

Construction of Flood Control Structure along Sta. Maria River, Sta. 04+900 - Sta. 05+050 (Poblacion - Macaiban Section), Santa Maria, Bulacan

Construction of Flood Control Structure along Sta. Maria River, Sta. 04+900 - Sta. 05+050 (Poblacion - Macaiban Section), Santa Maria, Bulacan is a DPWH-tracked public work in SANTA MARIA (BULACAN), BULACAN, Region III. Reported contract value: ₱48,998,501.05. Status: Reported complete (DPWH). Contractor on record: R A PAHATI CONST & SUPPLY INC. Figures trace to sumbong.

SANTA MARIA (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sta. Maria River, Sta. 04 + 900 - Sta. 05 + 050 ( Poblacion - Macaiban Section ) , Santa Maria, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0006660

₱9,979,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007287

₱1,460,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000163

₱1,078,312.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007288

₱135,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0016339

₱108,080.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

90 projects · ₱7.4B total · 11 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE, ELISEO TRINIDAD ANGELES BRIDGE CROSSING PAMPANGA RIVER, SA

Nueva Ecija 2nd DEO, Region III

2024₱235.2M
Past target date (DPWH On-Going)
No sat.

ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF FLYOVERS / INTERCHANGES / UNDERPASSES / LONG SPAN BRIDGES MOLINO-DAANG HARI FLYOVER, INCL. ROW (PHASE II), CAVITE

Region IV-A, Region IV-A

2018₱230.0M
Reported complete (DPWH)
No sat.

MFO-1 NAT'L. ROAD NETWORK SERVICES, NETWORK DEV'T., CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES, FLYOVER AT MOLINO-DAANG HARI ROAD INTERSECTION, CAVITE 2ND L.D. CAVITE PROVINCE

Region IV-A, Region IV-A

2016₱204.2M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ELISEO TRINIDAD ANGELES BRIDGE ALONG PAMPANGA RIVER (PHASE III), S

Nueva Ecija 2nd DEO, Region III

2024₱190.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION & MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-WIDENING OF PERMANENT BRIDGES INCLUDING ROW, TO MORE THAN 2-LANES, DONA JOSEFA BRIDGE (BO1310LZ) ALONG DAANG MAHARLIKA (LZ), NUEVA ECIJA 4TH LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA

Region III, Region III

2017₱187.2M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL BRIDGES - CONSTRUCTION OF THE ELISEO TRINIDAD ANGELES BRIDGE ALONG PAMPANGA RIVER, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2021₱183.3M
Reported complete (DPWH)
View all 90 projects →

4. Implementation

Contract Amount

₱48,998,501.05

Progress

Reported complete (DPWH)

Start Date

March 25, 2024

Target End

October 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.