GAA 2024 SSP24CF0128

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ELISEO TRINIDAD ANGELES BRIDGE ALONG PAMPANGA RIVER (PHASE III), S

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ELISEO TRINIDAD ANGELES BRIDGE ALONG PAMPANGA RIVER (PHASE III), S is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱190,093,430.68. Status: Past target date (DPWH On-Going). Contractor on record: R A PAHATI CONST & SUPPLY INC. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Gabion ) at Pampanga River, Barangay Bugnan, Gabaldon, Nueva Ecija
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-24-0017856

₱4,079,928.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

90 projects · ₱7.4B total · 11 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE, ELISEO TRINIDAD ANGELES BRIDGE CROSSING PAMPANGA RIVER, SA

Nueva Ecija 2nd DEO, Region III

2024₱235.2M
Past target date (DPWH On-Going)
No sat.

ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF FLYOVERS / INTERCHANGES / UNDERPASSES / LONG SPAN BRIDGES MOLINO-DAANG HARI FLYOVER, INCL. ROW (PHASE II), CAVITE

Region IV-A, Region IV-A

2018₱230.0M
Reported complete (DPWH)
No sat.

MFO-1 NAT'L. ROAD NETWORK SERVICES, NETWORK DEV'T., CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES, FLYOVER AT MOLINO-DAANG HARI ROAD INTERSECTION, CAVITE 2ND L.D. CAVITE PROVINCE

Region IV-A, Region IV-A

2016₱204.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION & MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-WIDENING OF PERMANENT BRIDGES INCLUDING ROW, TO MORE THAN 2-LANES, DONA JOSEFA BRIDGE (BO1310LZ) ALONG DAANG MAHARLIKA (LZ), NUEVA ECIJA 4TH LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA

Region III, Region III

2017₱187.2M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL BRIDGES - CONSTRUCTION OF THE ELISEO TRINIDAD ANGELES BRIDGE ALONG PAMPANGA RIVER, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2021₱183.3M
Reported complete (DPWH)
No sat.

CONCRETING OF MONKAYO-BOSTON ROAD, PACKAGE A, INCLUDING ROW, COMPOSTELA VALLEY

Region XI, Region XI

2018₱181.4M
Reported complete (DPWH)
View all 90 projects →

4. Implementation

Contract Amount

₱190,093,430.68

Progress

Past target date (DPWH On-Going)

Start Date

August 27, 2024

Target End

December 10, 2025

5. Audit