Roads23KA0082

OFF-CARRIAGEWAY IMPROVEMENT ALONG SAYRE HIGHWAY K1497+000 - K1499+106BRGY. PATPAT, MALAYBALAY CITY, BUKIDNON 2ND LD

OFF-CARRIAGEWAY IMPROVEMENT ALONG SAYRE HIGHWAY K1497+000 - K1499+106BRGY. PATPAT, MALAYBALAY CITY, BUKIDNON 2ND LD is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱56,399,999.81. Status: Reported complete (DPWH). Contractor on record: JT GAMOLO CONST INCORPORATION FORMERLY:J T GAMOLO CONST. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Sayre Highway (Malingon Creek), Barangay Bagontaas, Valencia City, Bukidnon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bukidnon 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

175 projects · ₱6.3B total · 0 flags

4. Implementation

Contract Amount

₱56,399,999.81

Progress

Reported complete (DPWH)

Start Date

January 31, 2023

Target End

September 19, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.