Flood Control and Drainage20DQ0021

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION ALONG CARMONA RIVER, PHASE II, WEST S

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION ALONG CARMONA RIVER, PHASE II, WEST S is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱48,249,659.42. Status: Reported complete (DPWH). Contractor on record: KLDS TRADING & CONST. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

36 projects · ₱2.2B total · 0 flags

4. Implementation

Contract Amount

₱48,249,659.42

Progress

Reported complete (DPWH)

Start Date

February 26, 2020

Target End

December 24, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.