Flood Control and Drainage17DN0030

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND REHABILITATION WITH SLOPE PROTECTION OF ROBINSON CREEK, BRGY. SAN JOSE, ANTIPOLO CITY, 2ND LD

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND REHABILITATION WITH SLOPE PROTECTION OF ROBINSON CREEK, BRGY. SAN JOSE, ANTIPOLO CITY, 2ND LD is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱19,012,836.76. Status: Reported complete (DPWH). Contractor on record: FRAMECON BUILDERS. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱7,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement/Construction of Flood Control Structures of Creek, NHA Ave., Dela Paz, Antipolo City, Rizal
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-17-0000692

₱100,000,000.00 · FY2017

Released to National Electrification Administration (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,012,836.76

Progress

Reported complete (DPWH)

Start Date

June 5, 2017

Target End

January 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.