Buildings and Facilities18NA0128

CONSTRUCTION OF 2 STY 8 CL SCHOOL BUILDING, RIZAL CES, BUENAVISTA, AGUSAN DEL NORTE

CONSTRUCTION OF 2 STY 8 CL SCHOOL BUILDING, RIZAL CES, BUENAVISTA, AGUSAN DEL NORTE is a DPWH-tracked public work in Agusan del Norte DEO, Region XIII. Reported contract value: ₱22,627,808.78. Status: Reported complete (DPWH). Contractor on record: J-R3 CONST AND SUPPLY. Figures trace to dpwh.

Agusan del Norte DEO, Region XIII
Region: Region XIII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱30,500

    Probable match · score 0.88

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXIII-18-0010655 · · release to the district office, not itemized per project

    Possible match · score 0.81

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18NA0128 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-06-15 → 2025-11-30

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · School building, cost per classroom (new school building)

₱2,828,476 per classroom= 2.0x the Region XIII median (n=254)

Contract cost ₱22,627,809 ÷ 8 classroom read from the DPWH title (“2 STY 8 CL”; classroom count in title). National percentile: 89. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 2 STY 8 CL SCHOOL BUILDING, RIZAL CES, BUENAVISTA, AGUSAN DEL NORTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Kalinawan - Tubay Riverdike, Agusan Del Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-18-0010655

₱0.00 · FY2018

Released to Division of Agusan del Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱22,627,808.78

Progress

Reported complete (DPWH)

Start Date

January 14, 2019

Target End

November 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.