Roads24CN0111

CONSTRUCTION OF ROAD, BRGY. BUHANGIN, BALER, AURORA

CONSTRUCTION OF ROAD, BRGY. BUHANGIN, BALER, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱59,400,000.00. Status: Past target date (DPWH On-Going). Contractor on record: IRC CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱50,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱58,134,664 · IRC CONSTRUCTION AND SUPPLIES

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    91% reported · imagery 2023-08-10 → 2023-08-10

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF ROAD, BRGY. BUHANGIN, BALER, AURORA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Calaocan, Dipaculao, Aurora
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Aurora DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱59,400,000.00

Progress

Past target date (DPWH On-Going)

Start Date

July 2, 2024

Target End

June 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.