Construction of Flood Mitigation Structure23DN0009

Construction of Flood Control Structure, Cupang (Downstream) Phase 2, Barangay Cupang, Antipolo City

Construction of Flood Control Structure, Cupang (Downstream) Phase 2, Barangay Cupang, Antipolo City is a DPWH-tracked public work in CITY OF ANTIPOLO (RIZAL), RIZAL, Region IV-A. Reported contract value: ₱48,999,987.97. Status: Reported complete (DPWH). Contractor on record: YPR GEN CONTRACTOR AND CONST SUPPLY INC / TOP KMC CONST AND SUPPLY CORP. Figures trace to sumbong.

CITY OF ANTIPOLO (RIZAL), RIZAL, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Cupang (Downstream) Phase 2, Barangay Cupang, Antipolo City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Rizal 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,999,987.97

Progress

Reported complete (DPWH)

Start Date

February 16, 2023

Target End

December 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.