Roads17M00071

ROAD OPENING OF SURALLAH-T'BOLI-SAN JOSE ROAD (GEN. SANTOS CITY) PACKAGE 4, BRGY. T'BOLI-BRGY. MAAN SECTION, T'BOLI, SOUTH COTABATO

ROAD OPENING OF SURALLAH-T'BOLI-SAN JOSE ROAD (GEN. SANTOS CITY) PACKAGE 4, BRGY. T'BOLI-BRGY. MAAN SECTION, T'BOLI, SOUTH COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱144,743,657.99. Status: Reported complete (DPWH). Contractor on record: VICENTE T LAO CONST. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱144,743,657.99

Progress

Reported complete (DPWH)

Start Date

June 7, 2017

Target End

November 5, 2019

5. Audit