Construction of Flood Mitigation Structure21OB0257

Pasig-Marikina River Channel Improvement Project, Phase V, Contract Package 4A - River Improvement Works Along Upper Marikina River (Upstream of Marikina Bridge) Sta. 15+450 to Sta. 15+600, Right Bank, Marikina City

Pasig-Marikina River Channel Improvement Project, Phase V, Contract Package 4A - River Improvement Works Along Upper Marikina River (Upstream of Marikina Bridge) Sta. 15+450 to Sta. 15+600, Right Bank, Marikina City is a DPWH-tracked public work in MARIKINA CITY, National Capital Region. Reported contract value: ₱91,626,579.72. Status: Reported complete (DPWH). Contractor on record: ROAD EDGE TRADING & DEVELOPMENT SERVICES. Figures trace to sumbong.

MARIKINA CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Flood Control River Wall along Polo River, Barangay Tagalag, Valenzuela City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008628

₱213,653,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013871

₱180,110,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013849

₱36,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0005956

₱1,804,051.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008606

₱251,872,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0007081

₱1,058,064.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0011289

₱1,006,625.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0009238

₱530,101.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0005957

₱167,446.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-21-0010927

₱1,131,141.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

83 projects · ₱5.7B total · 15 flags

4. Implementation

Contract Amount

₱91,626,579.72

Progress

Reported complete (DPWH)

Start Date

February 8, 2022

Target End

December 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.