Buildings and Facilities17MA0028

CLUSTER G- CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT) IN 1) BRGY. REMPES AND 2) BRGY. KIBLEG, 3) BRGY. BORONGOTAN AND 4) BRGY. BLENSONG, ALL IN UPI, MAGUINDANAO

CLUSTER G- CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT) IN 1) BRGY. REMPES AND 2) BRGY. KIBLEG, 3) BRGY. BORONGOTAN AND 4) BRGY. BLENSONG, ALL IN UPI, MAGUINDANAO is a DPWH-tracked public work in Cotabato City DEO, Region XII. Reported contract value: ₱6,404,755.80. Status: Reported complete (DPWH). Contractor on record: BRE CONST. Figures trace to dpwh.

Cotabato City DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-17-0007064

₱188,813.00 · FY2017

Released to Raniag High School To C. (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱6,404,755.80

Progress

Reported complete (DPWH)

Start Date

February 1, 2018

Target End

April 11, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.