Roads16BK0199

REPAIR/RESTORATION/IMPROVEMENT ALONG CORDON-AURORA BOUNDARY ROAD (S04745LZ), K0394+850 (RS) NAGTIPUNAN, QUIRINO

REPAIR/RESTORATION/IMPROVEMENT ALONG CORDON-AURORA BOUNDARY ROAD (S04745LZ), K0394+850 (RS) NAGTIPUNAN, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱2,526,765.37. Status: Reported complete (DPWH). Contractor on record: A P D CONST INC FORMERLY: APD CONST. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-ROVIII-16-0004539 · ₱560,000 · release to the district office, not itemized per project

    Possible match · score 0.77

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 16BK0199 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-09-01 → 2025-04-14

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REPAIR/RESTORATION/IMPROVEMENT ALONG CORDON-AURORA BOUNDARY ROAD (S04745LZ), K0394+850 (RS) NAGTIPUNAN, QUIRINO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0004539

₱560,000.00 · FY2016

Released to Southern Samar National Comprehensive High ScPS re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

355 projects · ₱12.1B total · 1 flags

Other projects by this contractor

No sat.

NETWORK DEV'T PROGRAM: CONST'N OF MISSING LINKS/NEW ROADS JCT. VICTORIA-MADDELA-ALICIA-KASIBU, NUEVA VIZCAYA ROAD, QUIRINO, STA. 0+000-STA. 4+500, AGLIPAY, QUIRINO

Region II, Region II

2018₱185.7M
Reported complete (DPWH)
No sat.

OO 1. NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROAD-JCT. ABBAG-GUINGIN BOUNDARY ROAD (BUCAO-LA CONWAP SECTION) QUIRINO, STA. 0+000-STA. 3+040 (CONCRETING, STA. 3+320-STA. 4+240 (OPENING), QUIRINO LONE DISTRICT

Region II, Region II

2018₱166.7M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - ARITAO-QUIRINO ROAD, PACKAGE 1, QUIRINO

Region II, Region II

2024₱158.9M
Reported complete (DPWH)
No sat.

MFO 1: NAT'L ROAD NETWORK SERVICES: NETWORK DEV'T: CONST'N OF MISSING GAPS CONNECTING NAT'L ROADS INCLUDING ROW, JCT. ABBAG-GUINGIN BDRY. ROAD (BUCAO-LA CONWAP SECTION) INCLUDING SLOPE PROTECTION, STA. 000+000-STA.001+680, STA. 002+220-STA.003+770, NAGTIP

Region II, Region II

2017₱142.0M
Reported complete (DPWH)
No sat.

MFO 3:MAINTENANCE AND CONSTRUCTION SERVICES OF OTHER INFRASTRUCTURES: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS-TO DECLARED TOURISM DESTINATIONS-NRJ GUNDAWAY-SUSONG DALAGA, ZAMORA SAN MARCOS-

Region II, Region II

2017₱141.7M
Reported complete (DPWH)
No sat.

MFO 1: NAT'L RD. NETWORK SERVICES: RD. UPGRADING(UNPAVED TO PAVED) BASED ON GRAVEL RD. STRATEGIES, TRAFIC BENCHMARK FOR UPGRADING TO PAVED RD. STANDARD(HDM 4-PROJ.ANALYSIS),TERTIARY RD., JCT. ABBAG-GUINGIN BDRY. RD.

Region II, Region II

2017₱133.8M
Reported complete (DPWH)
View all 355 projects →

4. Implementation

Contract Amount

₱2,526,765.37

Progress

Reported complete (DPWH)

Start Date

May 29, 2017

Target End

July 27, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.