Buildings and Facilities19HB0176

LOCAL INFRASTRUCTURE PROGRAM BUILDINGS AND OTHER STRUCTURE MULTI-PURPOSE/FACILITIES COMPLETION OF COVERED COURT BARANGAY BAGUMBAYAN, LOBOC, BOHOL

LOCAL INFRASTRUCTURE PROGRAM BUILDINGS AND OTHER STRUCTURE MULTI-PURPOSE/FACILITIES COMPLETION OF COVERED COURT BARANGAY BAGUMBAYAN, LOBOC, BOHOL is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱1,839,398.83. Status: Reported complete (DPWH). Contractor on record: RONNYL CONST. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-19-0011352

₱9,308,000.00 · FY2019

Released to Sikatuna National Agricultural High Sch (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

111 projects · ₱657.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM -REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS- TAGBILARAN EAST RD (TAGBILARAN-JAGNA) - K0206 + 000 - K0206 + 321, K

Bohol 3rd DEO, Region VII

2023₱34.0M
Reported complete (DPWH)
No sat.

CONCRETING OF BRGY. CORAZON FMR, BRGY. CORAZON, SAN MIGUEL, BOHOL

Bohol 2nd DEO, Region VII

2023₱29.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS- ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. POBLACION, UB

Bohol 2nd DEO, Region VII

2024₱26.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - JCT. TCSR POBLACION-LIBJO ROAD LEADING TO MIRRORS OF THE WORLD SIKATUNA AND SIKATUNA TREE PARK, SIKATUNA, BOHOL

Bohol 1st DEO, Region VII

2023₱26.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS LOAY INTERIOR RD - K0193 + 000 - K0194 + 000

Bohol 3rd DEO, Region VII

2025₱26.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - JCT. (LIR) QUINOGUITAN-SEVILLA-HANOP

Bohol 3rd DEO, Region VII

2024₱14.7M
Reported complete (DPWH)
View all 111 projects →

4. Implementation

Contract Amount

₱1,839,398.83

Progress

Reported complete (DPWH)

Start Date

August 28, 2019

Target End

November 15, 2019

5. Audit