Construction of Revetment22FE0042

Construction of Revetment (along Libmanan River) within Bicol River Basin, Brgy. Aslong, Libmanan, Camarines Sur

Construction of Revetment (along Libmanan River) within Bicol River Basin, Brgy. Aslong, Libmanan, Camarines Sur is a DPWH-tracked public work in LIBMANAN (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱48,015,655.63. Status: Reported complete (DPWH). Contractor on record: NFH CONST & SUPPLY. Figures trace to sumbong.

LIBMANAN (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Bagong Sirang, Pili, Camarines Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002963

₱613,385,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006800

₱5,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

50 projects · ₱4.0B total · 5 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR.) - K0681+580 - K0683+000, K0683+410 - K0684+440, K0684+750 - K0685+810, K0687+964 - K0688+092

Region VIII, Region VIII

2024₱250.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-IMELDA BOULEVARD, VIRAC, CATANDUANES, VIRAC, CATANDUANES (LONE DISTRICT)

Region V, Region V

2024₱232.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239-PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY ALONG DAANG MAHARLIKA (LZ)-K0456+(-892)-K0456+(-627), K0457+1741-K0457+2047, K0461+385-K0463+000

Region V, Region V

2024₱222.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY PACKAGE 19, CAMARINES SUR, PILI, CAMARINES SUR (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

MFO3-MAINTENANCE & CONSTRUCTION SERVICES OF OTHER INFRASTRUCTURES: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, DARAGA, PLACER-DIVISORIA, CAWAYAN ROAD, MASBATE PROVINCE

Region V, Region V

2017₱193.0M
Reported complete (DPWH)
No sat.

BRIDGE - WIDENING OF PERMANENT BRIDGES - PALANIT BR. (B00237SM) ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR.), NORTHERN SAMAR 1

Region VIII, Region VIII

2024₱192.9M
Past target date (DPWH On-Going)
View all 50 projects →

4. Implementation

Contract Amount

₱48,015,655.63

Progress

Reported complete (DPWH)

Start Date

March 16, 2022

Target End

October 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.