Buildings and Facilities16CL0026

CONSTRUCTION OF TWO STOREY 8CL SCHOOL BUILDING AT ROFULO M. LANDA HIGH SCHOOL (SALAZA NHS), PALAUIG,

CONSTRUCTION OF TWO STOREY 8CL SCHOOL BUILDING AT ROFULO M. LANDA HIGH SCHOOL (SALAZA NHS), PALAUIG, is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱9,460,713.13. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱18,137,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection/Flood Control at Bucao Dike, Botolan, Zambales
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-16-0036233

₱6,615,000.00 · FY2016

Released to Doña Hortencia S. Benedicto Memorial National HRel (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

16CL0026 - Construction of Two Storey 8CL School

₱9,460,713.31 · STO. CRISTO CONSTRUCTION AND TRADING

Contractor

A

490 projects · ₱18.9B total · 0 flags

Other projects by this contractor

View all 490 projects →

4. Implementation

Contract Amount

₱9,460,713.13

Progress

Reported complete (DPWH)

Start Date

July 15, 2016

Target End

December 11, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.