CONSTRUCTION OF BALIBAGAN WATER SYSTEM, IGBARAS, ILOILO

CONSTRUCTION OF BALIBAGAN WATER SYSTEM, IGBARAS, ILOILO is a DPWH-tracked public work in Iloilo 1st DEO, Region VI. Reported contract value: ₱1,974,656.60. Status: Reported complete (DPWH). Contractor on record: NOE'S BUILDERS. Figures trace to dpwh.

Iloilo 1st DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Tangyan River, Igbaras, Iloilo
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Iloilo 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,974,656.60

Progress

Reported complete (DPWH)

Start Date

April 6, 2021

Target End

June 28, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.