GAA 2017 MFO-217NA0035

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF FLOOD CONTROL STRUCTURE BRGY. POBLACION, TUBAY, AGUSAN DEL NORTE 2ND L.D.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF FLOOD CONTROL STRUCTURE BRGY. POBLACION, TUBAY, AGUSAN DEL NORTE 2ND L.D. is a DPWH-tracked public work in Agusan del Norte DEO, Region XIII. Reported contract value: ₱39,622,067.00. Status: Reported complete (DPWH). Contractor on record: GICAR CONST INC. Figures trace to dpwh.

Agusan del Norte DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/ Rehabilitation/ Improvement of Flood Control Structure, Brgy. Poblacion, Tubay, Agusan del Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-17-0012707

₱19,626,977.00 · FY2017

Released to Division of South Cotabato (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱39,622,067.00

Progress

Reported complete (DPWH)

Start Date

April 3, 2017

Target End

February 28, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.