Roads21L00170

BYPASS ROAD, JCT. MATTI (ALONG DAVAO - COT. ROAD) - JCT. AURORA (ALONG DIGOS - MAKAR ROAD), DAVAO DEL SUR

BYPASS ROAD, JCT. MATTI (ALONG DAVAO - COT. ROAD) - JCT. AURORA (ALONG DIGOS - MAKAR ROAD), DAVAO DEL SUR is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱27,145,847.77. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: P L SEBASTIAN CONST INC FORMERLY: P L SEBASTIAN CONST. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱27,145,847.77

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 4, 2022

Target End

December 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.