Construction of Flood Mitigation Structure22PC0063

Construction of Flood Control Structure in Brgy. Cadaclan, Calanasan, Apayao

Construction of Flood Control Structure in Brgy. Cadaclan, Calanasan, Apayao is a DPWH-tracked public work in CALANASAN (BAYAG) (APAYAO), APAYAO, Cordillera Administrative Region. Reported contract value: ₱6,827,260.01. Status: Reported complete (DPWH). Contractor on record: E C V CONST. Figures trace to sumbong.

CALANASAN (BAYAG) (APAYAO), APAYAO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱7,000

    Probable match · score 1.00

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-22-0002927 · ₱110,759,000

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-06-14 → 2025-03-13

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Apayao

Based on the coordinates published with the DPWH record and NOAH file Apayao.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱7,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure in Brgy. Cadaclan, Calanasan, Apayao
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002927

₱110,759,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

67 projects · ₱744.0M total · 0 flags

Other projects by this contractor

No sat.

OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS - FLOOD MNGT PROG-CON/REHAB OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONS OF CABICUNGAN RIVER BASIN FLOOD CONTROL STRUCTURE,DAPPAY SECTION, STA.12+090-STA.12+410(L/S),CAL

Apayao 2nd DEO, Cordillera Administrative Region

2025₱46.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM- REHAB/RECONS OF ROADS W/ SLIPS,SLOPES COLLAPSE,& LANDSLIDE-TERTIARY ROADS-CLAVERIA-CALANASAN-KABUGAO RD-K0626+605-K0626+670,K0628+513- K0628+577,K0634+554-K0634+600, K0635+343-K0

Apayao 2nd DEO, Cordillera Administrative Region

2025₱42.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONA LOUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF APAYAO RIVER BASINS AND PRINCI

Apayao 1st DEO, Cordillera Administrative Region

2024₱38.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO-ILOCOS NORTE RD - K0647 + 120 - K0647 + 320

Apayao 2nd DEO, Cordillera Administrative Region

2024₱33.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO-ILOCOS NORTE RD- K0650+700 - K0650+737, K065

Apayao 2nd DEO, Cordillera Administrative Region

2025₱30.2M
Past target date (DPWH On-Going)
No sat.

OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO (CALANASAN) - ILOCOS NORTE RD - K0619+650 - K0619+800

Apayao 2nd DEO, Cordillera Administrative Region

2024₱29.3M
Reported complete (100% progress, DPWH status On-Going)
View all 67 projects →

4. Implementation

Contract Amount

₱6,827,260.01

Progress

Reported complete (DPWH)

Start Date

March 25, 2022

Target End

October 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.