Flood Control and Drainage25OE0110

CONSTRUCTION OF RETARDING BASIN AT ESTERO DE MAYPAJO, TONDO, MANILA CITY (PHASE VI)

CONSTRUCTION OF RETARDING BASIN AT ESTERO DE MAYPAJO, TONDO, MANILA CITY (PHASE VI) is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱56,740,053.20. Status: Past target date (DPWH On-Going). Contractor on record: DAHL CONST CORP FORMERLY: DAHL CONST. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Maypajo, Barangay 186 & Barangay 187, Manila City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

North Manila DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱56,740,053.20

Progress

Past target date (DPWH On-Going)

Start Date

March 20, 2025

Target End

November 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.