Flood Control and Drainage24OB0185

CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER LAKESHORE AREA (PHASE 1), TAGUIG CITY

CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER LAKESHORE AREA (PHASE 1), TAGUIG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱94,569,660.72. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: DAHL CONST CORP FORMERLY: DAHL CONST. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Drainage System along Westbank Road, Manggahan Floodway, Pasig City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Metro Manila 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱94,569,660.72

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 29, 2024

Target End

January 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.