Buildings and Facilities20OB0171

CONSTRUCTION OF FOUR (4) STOREY TWELVE 12 CLASSROOM WITH ROOF DECK, ENLISTED MENS SIGNAL VILLAGE ELEMENTARY SCHOOL TAGUIG CITY

CONSTRUCTION OF FOUR (4) STOREY TWELVE 12 CLASSROOM WITH ROOF DECK, ENLISTED MENS SIGNAL VILLAGE ELEMENTARY SCHOOL TAGUIG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱34,566,172.31. Status: Reported complete (DPWH). Contractor on record: ST TIMOTHY CONST CORP. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2020 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱34,566,172 · ST TIMOTHY CONST CORP

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-03-25 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · School building, cost per classroom (new school building)

₱2,880,514 per classroom= 1.2x the National Capital Region median (n=289)

Contract cost ₱34,566,172 ÷ 12 classroom read from the DPWH title (“12 CLASSROOM”; classroom count in title). National percentile: 90. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FOUR (4) STOREY TWELVE 12 CLASSROOM WITH ROOF DECK, ENLISTED MENS SIGNAL VILLAGE ELEMENTARY SCHOOL TAGUIG CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Sapang Baho, Marikina City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Metro Manila 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Contract ID No. 20OB0171 Contract Name Construct

₱34,566,172.31 · ST TIMOTHY CONST CORP

Award / contract ref: 20OB0171

Contractor

F

942 projects · ₱44.1B total · 42 flags

Other projects by this contractor

No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, MANILA NORTH RD - K0578+640 - K0578+900 R/S

Region I, Region I

2023₱390.8M
Reported complete (DPWH)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS &/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. LIYANG, PILAR TO BRGY. BILOLO (PHASE 1), ORION, BATAA

Region III, Region III

2024₱305.7M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD AND CAUSEWAY FOR TOURISM ALONG AZAGRA PORT, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

CLUSTER 12: CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, ORIENTAL MINDORO, 12.1: CONST. OF BALITE R/C, BRGY. MALAMIG SECT., STA. 0+000-STA. 0+308.60; 12.2: CONST. OF CAWACAT R/C, TABUK SECT., BULALACAO, STA.0+000-STA. 0+324.3; 1

Region IV-B, Region IV-B

2022₱289.5M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CAJIDIOCAN PORT, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG POBLACION SAN FERNANDO, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
View all 942 projects →

4. Implementation

Contract Amount

₱34,566,172.31

Progress

Reported complete (DPWH)

Start Date

August 28, 2020

Target End

December 3, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.