Flood Control and Drainage18K00223

CLUSTER 19 CONST./REHAB. OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS&PRINCIPAL RIVERS BUK

CLUSTER 19 CONST./REHAB. OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS&PRINCIPAL RIVERS BUK is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱174,001,701.11. Status: Reported complete (DPWH). Contractor on record: PREMIUM MEGASTRUCTURES INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

99 projects · ₱12.6B total · 0 flags

4. Implementation

Contract Amount

₱174,001,701.11

Progress

Reported complete (DPWH)

Start Date

August 1, 2018

Target End

June 17, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.